CURRENT PROJECTS

Fulton County Maintenance and Transportation Facility – Ra-Lin and Associates General Contractor

  • This project involved site preparation for the construction of a new Maintenance and Transportation facility supporting 129 schools.
    • Demo of existing facilities, including three (3) homes on land purchased by the school district
    • Clearing and grubbing of 15+ acres
    • Erosion and sediment control across all phases of construction
    • Site utilities – storm, water, sanitary sewer
    • Excavation and grading to support installation of five (5) parking lots, a new transportation building, new maintenance building and an expanded bus shop
    • Site remediation of buried structures, supersaturated soils, buried trash and a burn pit

Task Order No. 1 – Astra Group – General Contractor

  • The purpose of this project is to ensure that sidewalks and ramps in identified areas are ADA compliant.  As such Earthbound’s scope involves:
    • Demolition of identified sections of sidewalks, driveways, curbs and gutter
    • Grading and installation of GAB to prepare subgrade for concrete
    • Adjusting water valve boxes, water meter boxes and manhole’s to grade
    • Finish grading and sodding as needed

B.W. JARRETT

  • In January 2018, contracted to complete the site preparation work for the Fort McPherson VA Parking Deck.  This work includes:
    • Erosion and sediment control
    • Clearing and grubbing
    • Demolition of the existing parking lot
    • Storm, sanitary and fire water utilities
    • Installation of the parking deck pad
    • Landscaping

COMPLETED PROJECTS

ST. PAUL AME CHURCH

  • Complete site preparation package for 43,000 SF church edifice expansion.  This package includes:
    • Erosion and sediment control
    • Clearing and grubbing
    • Utilities to 5’
    • Grading and installation of building pad
    • Demolition of 2,500 SF building
    • Removal of 48″ diameter tree
    • Grading and installation of stone driveway
    • Permanent grassing

YOUNG-LEVETT FUNERAL HOME

  • Completed early site work package which included:
    • Erosion and sediment control
    • Demolition of existing home
    • Clearing and grubbing
    • Rough grading for drainage
    • Installation and compaction of stone in preparation for asphalt
    • Rough and final grading

CLAYTON COUNTY FIRE STATION #9 (EARLY SITE WORK)

  • Contracted in August 2018 to complete the early site work for the Clayton County Fire Station #9
    • Demolition of concrete pillars and pump house
    • Erosion and sediment control
    • Clearing and Grubbing
    • Cut and fill
    • Grading
    • Compacting